A street festival needs asphalt, and the paperwork that gets it is written months before the stage arrives. Palm Beach County wants ninety working days to close a county road for longer than a day. Orlando will not let you take a lane at five in the afternoon.

01 — Find out who the street belongs to

A route that reads as one street is often three jurisdictions.

City, county and state roads are separate applications, and a festival route crosses between them without telling anyone.

Palm Beach County approves closures on county roads, and its own special event procedure says the approval covers county roads alone. Anything else on the route goes to the agency or owner that maintains it, on that agency’s own timetable.

Fort Lauderdale reviews road closures citywide under Chapter 25 of its ordinances, through the Transportation and Mobility Department, while the event itself is permitted through Parks and Recreation. Two departments, one date.

Miami permits events on city right-of-way and caps them at ten consecutive calendar days per organization per year, which sets the outer limit on a build-in, a run and a strike taken together.

Checking the map first costs nothing. Fort Lauderdale publishes LauderStreet, a map of road and sidewalk closures, so an applicant can see what is already shut on the date they want.

02 — The clock runs on hours closed, not on audience

Lead time follows how long the road stays shut, and the stage left standing overnight is what moves it.

In Palm Beach County the same festival is a thirty-working-day application or a ninety-working-day one.

The county publishes three deadlines for a special event on a county road. A closure of more than twenty-four hours needs a minimum of ninety working days in advance. A closure of less than twenty-four hours needs thirty. A minor closure under twelve hours needs ten.

Those bands count hours of closure, not hours of show. A Saturday street festival that loads in on Friday afternoon and strikes on Sunday morning has held the road for around forty hours, and sits in the ninety-working-day band. The same show, in and out inside one day, sits in the thirty.

So whether the stage comes down on Saturday night is settled in the spring, by whoever files the application. A producer asked about it in October is being asked to confirm a decision that was already taken.

The county also rejects what arrives half-finished. Its procedure states that an application not filled out completely, with all attachments included, will be rejected, which spends the lead time without buying anything.

03 — One lane is quicker to permit and narrower to use

Borrowing a lane shortens the application and takes both weekday peaks off the table.

Orlando bars lane closures through the morning and evening peaks, which pushes a load-in to midday or to the night.

Orlando asks for closure requests ten business days before a closure shorter than fourteen days, and fifteen business days before a longer one. Review then takes at least five business days once the documents are complete.

The restriction that shapes a schedule sits further down the same guide. No lane closures between 6 and 9 a.m. or 3 and 7 p.m., Monday through Friday, and none in inclement weather or on city-observed holidays and holiday weekends.

What is left is the middle of the day and the night, and night work carries a crew of its own. Orlando requires police officers and adequate lighting on site for nighttime operations that close lanes or roads, and says off-duty officers may be required.

Pedestrians stay in the plan throughout. The guide requires pedestrian control on one side of the road at all times, and temporary walkways, boardwalks or temporary sidewalks where that is not possible.

04 — A full closure adds notice and hardware

Doors to knock on and boards to set out, both of them weeks before the trucks.

Hand-delivered notice and message signs are production line items, booked long before the event week.

Orlando requires notification to affected residents and businesses, hand delivered, five to ten business days in advance depending on the length of the closure. Portable changeable message signs, where they are required, go in on the same five to ten day footing.

Both obligations land on somebody with a calendar. A crew that arrives on the Thursday finds the boards should have been out the week before, and the notice walked door to door before that.

05 — Three cities, three signatures on one plan

The qualification a traffic plan needs is set locally, stop by stop.

A route that plays three Florida cities meets a different standard in each of them.

Orlando asks every applicant for a copy of an Advanced FDOT MOT certificate, held by the person responsible for the setup and maintenance of the traffic control plan. A full intersection closure goes further: that plan is signed and sealed by a Florida registered Professional Engineer.

Fort Lauderdale asks for a copy of a Traffic Control Technician or Traffic Control Supervisor certification. The plan is drawn over a color aerial map, with FDOT index drawings or MUTCD typical applications attached for any detour, and conforms to the latest edition of FDOT design standards.

Miami asks for a maintenance of traffic plan from a certified traffic engineer, and a site plan mechanically drawn to quarter-inch scale on eleven-by-seventeen paper showing all adjacent streets.

Palm Beach County adds a signature from outside the traffic office. Its application requires written consent from the law enforcement agency with jurisdiction over the roadway, signed and dated, and a map no larger than legal size showing where the closure begins and ends.

06 — The approval is a calendar, and it can restart

In Fort Lauderdale a road closure waits on a meeting, and a corrected plan starts again at the back.

The event permit and the traffic plan run on two clocks, and both of them are published.

Under City Ordinance 15-181, an outdoor event that requests or requires a road closure in Fort Lauderdale goes through an approval process with the City Commission before an event permit can be issued. That is a meeting date on a published calendar, with the event information updated after each commission meeting.

The traffic plan runs alongside it on its own schedule. The city states that approval may take up to three weeks after all required documents are received. A rejected submittal, corrected and sent back, is treated as a new submittal, which may take up to three weeks more.

Miami fixes the outer date for the permit itself. An application for up to a thousand attendees is due at least thirty days before the event, and one for more than a thousand at least forty-five.

07 — What the permit decides on the ground

The approved drawing fixes the footprint before the stage plot is drawn.

Lane width, the hours the road is yours and the detour route all land back on the production.

A lane closure leaves live traffic beside the deck. The stage faces along the street rather than across it, the mix position has to sit inside the closed lane, and every cable crossing the open lane becomes a ramp and a signature.

A full closure gives the width to turn the stage across the street and to put the mix where the audience is. It carries the hand-delivered notice and the message boards with it, and in most of these cities a longer wait.

Either way, the drawing the city approves is the drawing the crew works to. Moving it on the day means another submittal, and in Fort Lauderdale that restarts a three-week clock on an event that is already loading in.

Where the figures come from

  • Ninety working days for a county road closure over 24 hours, thirty for under 24 hours, ten for a minor closure under 12 hours; written law enforcement consent, signed and dated; map no larger than legal size; approval covers county roads only; an incomplete application is rejected — Palm Beach County special event permit application procedure, discover.pbc.gov, read on 28 October 2026.
  • Outdoor events requesting or requiring road closures go through City Commission approval before an event permit is issued, under City Ordinance 15-181; road closures reviewed under Chapter 25; events permitted through Parks and Recreation; LauderStreet publishes current road and sidewalk closures — City of Fort Lauderdale, special event road closures, fortlauderdale.gov, read on 28 October 2026.
  • Traffic Control Technician or Traffic Control Supervisor certification; plan drawn over a color aerial map with FDOT index drawings or MUTCD typical applications for detours; plan conforms to the latest edition of FDOT design standards; approval may take up to three weeks after all documents are received, and a corrected resubmittal is treated as a new submittal — City of Fort Lauderdale, Maintenance of Traffic permit, fortlauderdale.gov, read on 28 October 2026.
  • No lane closures 6 to 9 a.m. or 3 to 7 p.m. Monday through Friday, none in inclement weather or on observed holidays; ten business days notice under fourteen days of closure and fifteen over; review at least five business days; hand-delivered resident and business notice five to ten business days ahead of a full road closure; message signs in place five to ten days ahead; Advanced FDOT MOT certificate for the person responsible for setup and maintenance; full intersection closures signed and sealed by a Florida registered Professional Engineer; pedestrian control maintained on one side of the road at all times — City of Orlando, temporary traffic control guide and closure request pages, orlando.gov, read on 28 October 2026.
  • Special event application at least thirty days before the event up to one thousand attendees and at least forty-five days above that; maintenance of traffic plan from a certified traffic engineer; site plan mechanically drawn to quarter-inch scale at eleven by seventeen inches showing all adjacent streets; city right-of-way events permitted up to ten consecutive calendar days per organization per year — City of Miami, special event permit, miami.gov, read on 28 October 2026.
09 — Start here

Tell us about your event.

The date, the venue, roughly how many people, and what has to happen in the space. We will reply within 24 hours.

Phone
561-750-4070
Also
954-978-8442
Email
[email protected]
Shop
500 Northeast 28th Court, Pompano Beach, FL 33064
Follow
InstagramFacebookLinkedIn