Event production in Homestead
a noise ordinance with no decibel in it, and an exemption that covers the show

Homestead has no noise chapter. The sound rule sits in the nuisances chapter, it contains no decibel figure anywhere, and the instrument it names for measuring a violation is a person with ordinary hearing standing at least fifty feet away. Then it exempts authorised activities on publicly owned property, and exempts any permitted outdoor show on top of that — before taking both back where the public property is privately operated. Much of that article is shared South Florida model text, and this page links the cities that carry it rather than claiming it. What is Homestead's own is everything built on top: four filing clocks, a twelve-inch stage permit, a ten-kilowatt generator permit, and a parks chapter with four consecutive articles repealed.

01 — There is no noise chapter

The chapters run 19 Nuisances, 20 Parks, 21 Personnel, 22 Public Improvements

Every other city on this programme keeps sound in a chapter of its own, or in a performance-standards division. Homestead keeps it as an article inside nuisances.

Open the Homestead Code of Ordinances and look for the heading every production company looks for first. It is not there. The chapter list goes Chapter 17 Miscellaneous Offenses, Chapter 18 Motor Vehicles and Traffic, Chapter 19 Nuisances, Chapter 20 Parks and Recreation, Chapter 21 Personnel, Chapter 22 Public Improvements. No chapter in this code is called noise.

The sound rule is Chapter 19, Article II, sections 19-21 through 19-27, adopted by Ordinance No. 99-04-19 on 3 May 1999 and carrying that same adoption line at the foot of every section in the article. Section 19-21(b) sets its reach in one line: this article shall pertain to all sound originating within the city. There is no second sound standard elsewhere in the code to reconcile it with.

That placement is not cosmetic. An article inside a nuisances chapter is drafted to abate a disturbance after someone complains, not to set a design target in advance. Palm Beach Gardens puts its standard in a performance-standards division of the land development regulations, where a number exists to be designed to. Homestead's sits beside abandoned-property abatement and hanging laundry in front yards, and it reads exactly like what it is.

02 — No decibel figure appears anywhere in it

The primary means of measurement is a reasonable person with normal hearing

Section 19-25(a), in full, and it is the whole instrument.

Section 19-25 is headed measurement procedures, which raises an expectation the section does not meet. Subsection (a) reads: the primary means of measurement shall be by ordinary, auditory senses of a reasonable person with normal sensitivities, so long as any mechanical device does not enhance their hearing, such as a microphone or hearing aid.

There is no A-weighted table, no octave-band row, no averaging period, no exceedance allowance, no impulsive or tonal penalty and no reference to a sound level meter standard. Search the entire article for a decibel value and the count is zero. What governs instead is the definition in section 19-22 of a noise disturbance: any sound that is so excessive, loud or disturbing that it causes an adverse psychological or physiological effect on humans, or unnecessarily disturbs or interferes with the enjoyment of life or property, including outdoor recreation. Section 19-23(a) then prohibits causing one, by any method or device.

That sentence is not Homestead's own drafting, and it is worth saying so. The identical wording sits in Boynton Beach, and reasonable-listener clauses of the same family run through Doral and Sunrise. This is a model ordinance circulating between South Florida cities, and most of Homestead's noise article is a copy of it.

What differs is what sits behind the sentence. In Boynton Beach the reasonable-person test is a backstop in front of a numeric table, and the table is where the argument is actually had. In Homestead there is no table behind it. Search the entire article for a decibel value and the count is zero. The same borrowed sentence that is a long-stop elsewhere is, here, the whole instrument — and nothing in this city tells a sound designer what number to hold, because the city has not written one down.

The practical consequence runs in two directions at once. There is no figure to be caught above, and there is no figure to point at when a neighbour calls. A show is defensible here on the quality of what the property line hears rather than on a reading, which moves the work upstream into cardioid subwoofer arrays, rear rejection and stage orientation, and out of the hands of a meter operator on the night.

03 — Fifty feet, in a straight line

The only number in the measurement section is a distance, and it is a floor

Section 19-25(b) sets where a listener may stand, not what they may hear.

Section 19-25(b): the measurement shall be taken on, or as near as possible to, the real property line of the property upon which the sound source is located, and in any event from a location not less than fifty (50) feet from the sound source measured in a straight line.

The first half of that sentence is shared model text — Sunrise carries it word for word. The fifty-foot minimum is the part that does not appear on any other city page this programme has built. Read it as two instructions that can disagree. The default position is the property line of the source. The override is a hard minimum of fifty feet from the source itself. Where a stage sits closer than fifty feet to its own boundary — a downtown street closure, a plaza activation, a park whose usable flat ground runs to the fence — the fifty-foot floor moves the assessment point off the property line and away from the source.

Section 19-23(c) handles multifamily dwellings separately and in the opposite spirit: sound is judged when perceived within the center of an adjacent intrabuilding dwelling receiving the sounds, with the doors and windows of the room closed. Two assessment geometries in one article, one outdoor and distance-floored, one indoor and closed-window.

Section 19-25(b) requires the assessment point to be at least fifty feet from the sound source in a straight line.

A downtown Homestead site can easily put a stage within fifty feet of the opposite kerb line.

On that site the property line is inside the floor, so the assessment point is pushed outward to the fifty-foot radius.

Inverse-square spreading gives roughly six decibels for each doubling of distance from a point source, so the first fifty feet is where most of the available loss lives.

On a tight Homestead site the fifty-foot minimum is worth having on the drawing before anything is trucked. Where the boundary is closer than the floor, the point the city listens from is set by the ordinance rather than by the site, and the stage position decides what reaches it.

04 — The exemption that covers the show

Authorised activity on publicly owned property is exempt from the article

Section 19-24(c), and then section 19-24(j) exempts the permitted outdoor show a second time.

Section 19-24 lists the exemptions. Two of them are the whole argument for an event in this city.

Subsection (c): activities on or in city-owned and school athletic facilities, and on or in publicly owned property and facilities, when such activities have been authorized by the owners of such properties or facilities or their agents, except where such publicly owned properties are under private operation pursuant to a lease or concession agreement.

Subsection (j): any sound emanating from any circus, carnival or outdoor show permitted pursuant to the provisions of the City Code.

Subsection (c) is shared drafting again: Doral carries it verbatim, carve-out included. Linked rather than claimed. What changes between the two cities is not the clause but what it is an exemption from.

Take the two subsections at their plain words. A permitted festival on a Homestead city park is an authorised activity on publicly owned property, and it is also an outdoor show permitted pursuant to the City Code. On both routes it is exempt from the noise article rather than regulated by it. That is the inverse of the common arrangement, where a permit buys a time-limited departure from a table that still applies. Here the authorisation does not raise a limit. It removes the activity from an article that had no limit to raise.

It also explains the shape of everything downstream. A city that exempts its permitted events from its own sound rule has no reason to write a decibel table, and every reason to put its real conditions into the permit document instead. Which is precisely where Homestead has put them.

05 — And the clause that takes it back

Private operation under a lease or concession ends the exemption

Two sections, written twenty-seven years apart from the venue arrangements they now meet, point the same way.

The exemption in section 19-24(c) carries a carve-out in its own final clause: except where such publicly owned properties are under private operation pursuant to a lease or concession agreement. Section 19-27(c), at the far end of the article, closes the same loop from the other side: this section shall also apply to private entities leasing city-owned property.

So the question that decides which regime an event sits under is not whether the ground is public. It is who operates the venue, and under what instrument. That is a question about a contract, and contracts are not published in the code.

One Homestead venue states the arrangement on its own pages. The Seminole Theatre at 18 N. Krome Avenue publishes a footer reading Managed by OVG Facilities alongside City of Homestead — a city asset under named third-party management. Its rental pages describe a 420-seat auditorium on two levels with a fly system, an orchestra pit, dressing rooms and in-house lighting, audio and projection systems; a covered outdoor Terrace overlooking the adjacent Losner Park; and two mixed-use studios. The Terrace is the part that matters for this section, because it is outdoors, it is amplifiable, and it looks onto the city's own downtown event lawn.

Whether a particular management agreement is a lease or concession within the meaning of section 19-24(c) is a question for the city and the operator, and this page does not answer it. The point is that the question exists and is answerable in advance. On a city-owned site in Homestead the first thing worth establishing is not the sound limit. It is whether the exemption reaches the site at all, because if it does not, the event is back inside an article whose only measuring instrument is a complainant.

06 — The waiver goes to the elected body

A temporary noise permit follows a public hearing before the city council

Except where section 19-27(e) sends it to the city manager instead. Both sentences are in force.

Section 19-27 opens by describing a temporary permit to allow noise otherwise prohibited by the article, granted where the activity does not significantly endanger the health, safety and tranquility of the surrounding neighborhood, carrying all conditions and the period for which it is granted. Then it says how: such departures may be granted, following a public hearing before the city council.

Four paragraphs later, subsection (e) says something else. Permit applications for nonresidential property shall be reviewed by the city manager or his/her designee using the above criteria. Subsection (f) then gives an aggrieved applicant on nonresidential property a right of appeal to the city council at its next available meeting, which only makes sense if council was not the first decision-maker.

The preamble routes every departure through a public hearing. Subsection (e) routes the nonresidential ones — which is to say essentially all of them — through an administrative desk with council as appeal. Nothing in the section reconciles the two, and the practical difference is weeks: an administrative review turns in days, a council agenda item does not.

Quoted as published, not resolved. The defensible planning assumption is the slower of the two readings, because the faster one cannot be relied on by a promoter who has not asked. Establishing which route a given application takes is a single phone call, and it is worth making it before a date is announced rather than after.

07 — Three days, three a year, and not on the content

The limits on a temporary noise permit are counts, not levels

Section 19-27(b), (c) and (d).

Where a temporary permit is available, section 19-27(c) bounds it. It applies where an applicant has previously met all of the city's requirements for obtaining any required special event permits and the event cannot be performed or accomplished in a manner which would comply with this Article — so the special event permit comes first and the noise permit sits on top of it, never instead of it.

Such permits may be issued for a period of time not to exceed three (3) days, and no more than three (3) temporary permits for the conduct of special events which violate the prohibitions in this article shall be issued for a particular location on private property within any twelve-month period. The cap attaches to the location, not to the promoter — a venue that has spent its three has spent them for everyone. Construction departures under subsection (b) carry the same three-day ceiling unless otherwise authorized by the city council.

Subsection (d) sets the ground for refusal and then fences it: a permit may be denied if council finds the activity will result in a private or public nuisance on any adjoining or receiving property, but a permit may not be denied on the basis of the content of the proposed sound. That content-neutrality wording also appears on Hollywood, so it travels with the model rather than originating here — but it does the same work either way, narrowing the refusal to impact rather than to programme.

Failure to comply with any condition of a temporary permit is itself a violation under subsection (g), with enforcement and penalties following. The conditions written on the permit are therefore the operative sound standard for that event, and they are the only numbers in this system that will ever be specific.

08 — The performer is named personally

Section 19-26(b) reaches past the promoter to the person at the console

Two sentences, and the second one names a job rather than a party to a contract.

Section 19-26 is headed responsible party and has two subsections. The first is conventional: no person shall own, engage in or manage, or be in charge of any business premise, however temporarily, that creates a noise disturbance. The phrase however temporarily is doing real work — it reaches a site that is a business premise only for the weekend.

The second is not conventional. No musical performer, disc jockey or other person making a public presentation shall produce amplified sound upon any business premise, however temporarily, that creates a noise disturbance.

Both subsections appear verbatim on Sunrise, so this is the model ordinance again rather than a Homestead invention — which is exactly why it is worth reading rather than skipping. The drafting names the person producing the amplified sound in the ordinance itself, independently of who holds the permit, in at least two of the cities on this list. That is a thing to have established before a touring act's rider arrives asserting that compliance is somebody else's line item, and it is a reason to put the condition sheet in front of the engineer rather than only the promoter.

09 — Three desks, one permit, and a definition keyed to the park

The city describes its special event permit in three places and routes it three ways

City Manager's Office, Development Services, and the Parks and Recreation Special Events Coordinator.

The city's Special Events Division page states that the division operates within the City Manager's Office and serves as the central hub for planning, coordinating, producing and delivering public events on behalf of the city. The city's Special Event Permit page states that the Development Services Department is responsible for issuing Special Event permit within the City of Homestead, and gives the Business Services Division as the contact. The city's own Special Events Handbook directs completed applications to the Special Events Coordinator, City of Homestead Parks and Recreation Department, 350 SE 6 Avenue.

Three municipal pages, three offices. They are describing different functions — producing the city's own events, issuing the permit instrument, and receiving the application — but a promoter reading them in sequence is reading three different front doors, and the handbook and the permit page give different departments for the same filing.

The definition is the other thing to read carefully. The handbook: any event or activity that temporarily occurs in a public park that is open to the general public is considered a Special Event. No attendance threshold appears in that sentence. Miramar triggers on a headcount; Palm Beach Gardens triggers at twelve people. Homestead triggers on where you are and whether the public can walk in. A twenty-person ceremony in a city park is inside the regime; a two-thousand-person event on private ground is reached by a different route.

The permit package named on the city's page is a Special Event Permit Application, a Letter of Intent, a Letter of Consent, a Certificate of Insurance, a Road Closure Permit if required and a Tent Permit if required, with off-duty police required in some instances. The handbook adds the application fee, an event map or layout, a written event narrative, a clean-up plan naming the responsible individuals and the disposal point for waste including cooking oils and grey water, a first aid plan, and a site plan.

10 — Twenty-one, forty-five, sixty, one hundred and twenty

Four filing clocks, set by attendance and by the number of days

And the band is chosen from a number written down before the marketing has run.

The handbook opens by saying the application process can begin twelve (12) months in advance with a minimum of twenty-one (21) days prior to the event date depending on the type of event, and warns that applications filed inside twenty-one days may not receive the necessary approvals from the required City Departments and may be rejected. Then it bands the deadline four ways:

A one-day event up to 500 attendees: twenty-one days. A one-to-three-day event up to 2,000 attendees: forty-five days. A one-to-six-day event up to 5,000 attendees: sixty days. A major event above 5,000 attendees, which expressly includes anything running over seven days: one hundred and twenty days.

Two variables set the band, not one. Duration can move an event up a clock on its own: a three-day event for four hundred people is not a twenty-one-day filing, because the twenty-one-day band is one day only. That catches the shape of job this city actually produces — a weekend festival with a modest crowd lands at forty-five days rather than twenty-one on duration alone.

The back end has its own date. Once an application is approved, insurance and all event fees including the security deposit must be turned in ten (10) days prior to the event date, and the handbook is explicit that everything must be turned in to be processed before receiving the final special event permit. The permit must be displayed at the event site and readily accessible for review. A deposit returns two to four weeks after, where there is no damage.

A two-day community festival projects 1,800 attendees, which sits in the up-to-2,000 band at forty-five days.

Programming grows and the realistic projection moves to 2,400, which belongs in the up-to-5,000 band at sixty days.

The sixty-day deadline has already passed by the time the projection moves, and the handbook warns that late filings may be rejected.

Separately, the off-duty officer count is set by the Homestead Police Department rather than by the applicant, and must be paid ten days out.

File to the higher band from the start. The clock is set by a number entered on a form months before that number is knowable, and in Homestead the duration of the event can move the band without the crowd moving at all.

11 — Twelve inches, ten kilowatts, one hundred and twenty square feet

Three thresholds that put a production in front of the building department

All three are in the handbook's additional permits list, and the stage one is the lowest on this programme.

The handbook's section 2 lists the permits a special event may need beyond the special event permit itself. Three of them are structural, and all three are addressed to the City of Homestead Development Services Department Building Safety Division.

Stage. When required: using a portable stage taller than 12". Twelve inches. Not a span, not a height above grade measured in feet, not a deck area — a one-foot riser. A single stage deck on standard legs clears that threshold, and so does a drum riser.

Generator. When required: using a generator larger than 10 kw. Ten kilowatts is a small machine. It is the sort of unit that runs a modest PA and a few practicals and nothing else; anything carrying a lighting rig, a video wall or a second system is over the line by a wide margin.

Tents and canopies. When required: temporary structures that cover an area greater than 120 square feet including connecting areas or spaces with a common means of egress or entrance which are used or intended to be use for the gather together of 10 or more persons. A single ten-by-ten pop-up is under. Two of them sharing an entrance, or one ten-by-twenty, is over.

A small outdoor stage in Homestead is almost always taller than twelve inches, so it requires a stage permit from Building Safety.

Any show with a lighting rig or a video wall needs more than ten kilowatts, so it requires an electrical permit from the same division.

Production tenting usually exceeds one hundred and twenty square feet once canopies are joined, so it requires a building permit from the same division.

None of these is issued by the office that takes the special event application, and none appears on the special event permit itself.

In Homestead a normal small festival build is three separate building-department permits sitting behind one special event permit. The lead time that matters is not the twenty-one days on the handbook's first page — it is whoever is slowest among four desks, and the application that triggers them has to name the stage height, the generator size and the tent area to start the clocks at all.

12 — The city sells the power and still will not promise it

Homestead generates its own electricity, and tells event applicants to bring a generator

HPS Energy has run a municipal power plant here since 1916. The parks rental page says bring your own.

Homestead is one of a small number of Florida cities that owns its electric utility outright. The city's HPS Energy page states that the utility generates, distributes, and sells energy services, operates and maintains a power plant, and is responsible for constructing new electrical infrastructure as well as maintaining the electrical poles, wires, transformers, and street lights in its service area. It has served the city since 1916, held a one-time status as one of the largest municipal diesel-power generating plants in the United States, and now runs all ten of our power-generating units on natural gas. The utility is a recognised Reliable Public Power Provider.

Now read what the same city tells an event applicant. The handbook: the City of Homestead may be able to provide limited electrical services to special events at specific venues. Applicant should consult directly with the Special Events Coordinator to discuss all electrical needs for their event. May be able to. Limited. Specific venues.

The parks rental page is blunter. Against James Archer Smith Park, JD Redd Park and Mayor Roscoe Warren Park, the published details read must provide insurance and generator — the city stating in writing, venue by venue, that the renter brings the power. The same page adds a detail nobody invents: at Mayor Roscoe Warren Park, 2 10x10 tents are allowed with your rental and no items can be set-up in the retention ponds.

A city that makes its own electricity and still writes "must provide generator" beside three of its own parks has told you what the distribution looks like at the point of use. The site plan requirement closes it: the handbook requires the map to show source of electrical supply and service, including permanent electrical power sources and portable generators. Power is a drawing item in Homestead, decided at application, and it collides with the ten-kilowatt permit threshold in the section above the moment the rig is bigger than a speech system.

13 — The agencies that are not the city

Fire and pyrotechnics go to the county, drones go to Risk Management, officers go to the FOP

Three of the decisions that can stop a show are made outside City Hall.

Fire. The handbook routes open flames including cooking, spinning, fire fingers, staff to an Open Burn Permit, and any display of fireworks or other pyrotechnics to a Display of Fireworks, Pyrotechnics, and/or Flame Effects Permit — both from Miami-Dade Fire Rescue, not from a city department. First aid is the same story: the applicant must provide a plan and must check with Miami Dade Fire Rescue to determine if their presence is required for larger attendance events. The agency that decides whether a show has standby cover is a county agency with its own calendar.

Drones. Not in a filming section, not in a safety section — in the insurance paragraph of the event guidelines, as its own closing sentence: unmanned aerial vehicle use strictly prohibited unless specific written approval obtained from City Risk Management. A default prohibition, lifted only in writing, by the office that handles the city's liability rather than by the office that issues the permit. Aerial coverage in Homestead is a risk conversation started early or not had at all.

Officers. The handbook is specific and the arithmetic is worth having in advance. The Homestead Police Department shall be the final authority in determining the minimum number of officers required to police a particular event. If more than three (3) officers are hired, a supervisor must also be hired. The Fraternal Order of Police administers the off-duty programme and must be compensated ten (10) days prior to the event. Running fifteen minutes or more past the scheduled end adds hours. Cancelling an officer inside twenty-four (24) hours incurs a four-hour minimum. The parks rental page adds that a police contract may be required for the Harris Field Barn Pavilion and Losner Park specifically, with coverage by Homestead Police only.

Two more operational constraints sit in the same document and both land on the production. Neighborhood streets are prohibited from being used for event parking, which moves the crew and vendor fleet onto the site plan rather than onto the surrounding grid. And the city publishes a sanitation table rather than a rule of thumb: one portable restroom for every 200 people, five percent of them accessible, with a published grid running from a peak crowd of 500 to one of 5,000 against average dwell times of one to four hours — seventeen units at the top corner.

14 — The rooms, the reserved articles, and the numbers nobody publishes

Four consecutive articles of the parks chapter say RESERVED

Which is why the handbook carries the weight the code does not.

Chapter 20 of the code is Parks and Recreation. Its article list reads: Article I in general, Article II fees and charges, Article III reserved, Article IV reserved, Article V reserved, Article VI reserved, Article VII smoke-free parks. Four consecutive repealed articles, and what survives is a fee schedule, a definitions-and-general article, and a smoking rule adopted in 2026.

That is the structural fact underneath this whole page. Homestead's park and event regulation does not live in its code. It lives in a handbook updated July 2022 and in the rental conditions published beside each facility — documents a city can revise without an ordinance, and which therefore have to be re-read rather than remembered. The code's own fee schedule still lists a four-foot-by-eight-foot portable stage riser among the items the city rents by the day, which is the level of detail the parks articles used to carry and no longer do.

The venues publish unevenly. The Seminole Theatre is the best documented: a 420-seat auditorium on two levels with a fly system, orchestra pit, dressing rooms and in-house lighting, audio and projection systems, plus a covered outdoor terrace over Losner Park and two mixed-use studios. It does not publish a proscenium width, a grid height, a pit depth, a house power service, or whether a visiting production may bring its own control and tie into the house rig.

The Homestead Sports Complex is a 130-acre site at 1601 SE 28th Avenue, and the city's published master plan for its phased redevelopment lists an event stage among the amenities, along with artificial turf lighted soccer fields, a rubberised competition running track, lakeside picnic pavilions, a restroom and concession building and shaded spectator seating. That page is written as a forward plan rather than an inventory, so what is standing on any given date is a question for the Parks office rather than for a web page. Harris Field Park carries a stadium, a gymnasium and a barn pavilion in the rental schedule, with no dimensions attached to any of them.

Homestead-Miami Speedway publishes its track history page with two figures on it — track length 1.5 miles and banking 18-20 degree variable banking. That is geometry for a racing series. It is not load-in access, infield power, rigging capability or what a promoter may bring.

Not one Homestead venue, municipal or private, publishes a ceiling or trim height, a dock or door dimension, a point load or a service amperage. Stated here rather than guessed at. Each of those has to be walked and measured, and on a city-owned site in this city the walk carries the prior question from section 05 with it — who operates the venue, and under what instrument.

Where the figures come from

  • No chapter of the Homestead Code of Ordinances is titled noise; the sound standard is an article of the nuisances chapter, pertaining to all sound originating within the city — City of Homestead Code of Ordinances, Part II, Chapter 19, Article II, sections 19-21 through 19-27, adopted by Ord. No. 99-04-19, 5-3-99
  • Primary means of measurement is the ordinary auditory senses of a reasonable person with normal sensitivities, unaided by any mechanical device such as a microphone or hearing aid; no decibel value appears anywhere in the article. The quoted sentence is shared model text also carried by Boynton Beach, where it sits in front of a numeric table — Code of Ordinances section 19-25(a), Measurement procedures
  • Measurement taken at or as near as possible to the real property line of the source property, and in any event from not less than fifty feet from the sound source measured in a straight line — Code of Ordinances section 19-25(b)
  • Noise disturbance means any sound so excessive, loud or disturbing that it causes an adverse psychological or physiological effect on humans, or unnecessarily disturbs or interferes with the enjoyment of life or property, including outdoor recreation — Code of Ordinances section 19-22, Definitions, and section 19-23(a), Prohibited acts
  • Multifamily sound judged when perceived within the center of an adjacent intrabuilding dwelling with doors and windows closed — Code of Ordinances section 19-23(c)
  • Exempt: authorised activities on city-owned and school athletic facilities and on publicly owned property, except where under private operation pursuant to a lease or concession agreement. Shared model text, carried verbatim by Doral — Code of Ordinances section 19-24(c), Exemptions
  • Exempt: any sound emanating from any circus, carnival or outdoor show permitted pursuant to the provisions of the City Code; construction on private property and powered garden tools exempt 7:00 a.m. to 7:00 p.m. — Code of Ordinances section 19-24(j), (h) and (i)
  • Temporary noise permits granted following a public hearing before the city council in the section preamble, while applications for nonresidential property are reviewed by the city manager or designee with a right of appeal to council at its next available meeting — Code of Ordinances section 19-27 preamble, (e) and (f), Temporary permits and special events
  • Temporary permit not to exceed three days; no more than three per particular location on private property in any twelve-month period; applies also to private entities leasing city-owned property; may not be denied on the basis of the content of the proposed sound — Code of Ordinances section 19-27(b), (c) and (d)
  • No musical performer, disc jockey or other person making a public presentation shall produce amplified sound upon any business premise, however temporarily, that creates a noise disturbance. Shared model text, carried verbatim by Sunrise — Code of Ordinances section 19-26(b), Responsible party
  • Chapter 20, Parks and Recreation: Articles III, IV, V and VI are each RESERVED; surviving articles are in general, fees and charges, and smoke-free parks; the fee schedule lists a four-by-eight-foot portable stage riser among daily rental items — Code of Ordinances Chapter 20, article list and section 20-11, Recreational fees
  • Any event or activity that temporarily occurs in a public park open to the general public is a Special Event; process may begin twelve months ahead with a twenty-one day minimum; applications filed later may be rejected — City of Homestead Special Events Handbook, updated July 2022
  • Filing deadlines: twenty-one days for a one-day event up to 500 attendees; forty-five days for a one-to-three-day event up to 2,000; sixty days for a one-to-six-day event up to 5,000; one hundred and twenty days for a major event above 5,000 or running over seven days — Special Events Handbook, Application Fees, Due Date and Security Deposit
  • Insurance and all event fees due ten days prior to the event date and required before the final permit issues; permit must be displayed at the event site and readily accessible for review; deposit returned two to four weeks after where there is no damage — Special Events Handbook, Section 1
  • Stage permit required for a portable stage taller than 12 inches; electrical permit for a generator larger than 10 kw; building permit for a tent or canopy covering more than 120 square feet intended for the gathering of 10 or more persons — all from Development Services, Building Safety Division — Special Events Handbook, Section 2, Additional Permits
  • Open flames and any fireworks, pyrotechnics or flame effects permitted by Miami-Dade Fire Rescue; applicant must check with Miami-Dade Fire Rescue whether its presence is required for larger attendance events — Special Events Handbook, Section 2 and First Aid
  • Unmanned aerial vehicle use strictly prohibited unless specific written approval obtained from City Risk Management, stated within the insurance paragraph; commercial general liability at a published per-occurrence minimum, city as additional insured, coverage primary and non-contributory — Special Events Handbook, Section 3, Insurance
  • City may be able to provide limited electrical services at specific venues; site plan must show source of electrical supply and service including permanent power sources and portable generators — Special Events Handbook, Electrical and Site Plan/Sketch
  • Homestead Police Department is final authority on minimum officer numbers; a supervisor must be hired where more than three officers are hired; FOP administers and is compensated ten days prior; an extension of fifteen minutes or more adds hours; cancellation inside twenty-four hours incurs a four-hour minimum — Special Events Handbook, Off-Duty Police Officers
  • Neighborhood streets prohibited from being used for event parking; one portable restroom per 200 people with five percent accessible, against a published grid from 500 to 5,000 peak crowd and one to four hours average dwell — Special Events Handbook, Parking and Restrooms/Portable Toilets
  • James Archer Smith Park, JD Redd Park and Mayor Roscoe Warren Park rental details state the renter must provide insurance and generator; two ten-by-ten tents allowed at Mayor Roscoe Warren Park and no items may be set up in the retention ponds; police contract may be required for Harris Field Barn Pavilion and Losner Park only, Homestead Police only — City of Homestead, Renting Parks & Facilities
  • HPS Energy generates, distributes and sells energy services, has served the city since 1916, once held status as one of the largest municipal diesel-power generating plants in the United States, and runs all ten power-generating units on natural gas — City of Homestead, HPS Energy | Electric Services
  • Seminole Theatre: 420-seat auditorium on two levels with a fly system, orchestra pit, dressing rooms and in-house lighting, audio and projection systems; covered outdoor terrace overlooking Losner Park; two mixed-use studios; 18 N. Krome Avenue; site footer states Managed by OVG Facilities and City of Homestead — Seminole Theatre, venue rental pages and site footer
  • Homestead Sports Complex: 130-acre facility at 1601 SE 28th Avenue, phased redevelopment master plan listing an event stage, artificial turf lighted soccer fields, a rubberised competition running track, lakeside picnic pavilions and a restroom and concession building — City of Homestead, Homestead Sports Complex
  • Homestead-Miami Speedway publishes track length 1.5 miles and 18-20 degree variable banking; no ceiling or trim height, dock or door dimension, point load, service amperage or in-house audio-visual exclusivity is published by any Homestead venue — Homestead-Miami Speedway, Track History; and a reading of every Homestead venue page cited above
15 — Start here

Tell us about your event.

The date, the venue, roughly how many people, and what has to happen in the space. We will reply within 24 hours.

Phone
561-750-4070
Also
954-978-8442
Email
[email protected]
Shop
500 Northeast 28th Court, Pompano Beach, FL 33064
Follow
InstagramFacebookLinkedIn